Timeline
May 19, 2006:
- 8:32 PM Ticket #13 ([INITIAL.C] Note) created by
- Nella creazione del processo "test" ricordarsi di _ABILITARE_ tutti …
- 8:29 PM Ticket #8 (Controllo parametri in ingresso) reopened by
- 8:28 PM Ticket #8 (Controllo parametri in ingresso) closed by
- wontfix
May 16, 2006:
Apr 20, 2006:
- 4:21 PM Ticket #9 (Scope e visibilita`) closed by
- fixed
- 2:53 PM Ticket #10 (Architettura del progetto) closed by
- fixed
- 2:49 PM Ticket #11 (mergare kaya-ast nel tronco) closed by
- fixed
Apr 19, 2006:
- 2:46 PM WikiStart edited by
- (diff)
- 4:39 AM Milestone Phase 1 completed
- La phase 1 prevede la realizzazione delle strutture base del …